R747-2B – Dubai Airport Roads Improvements Phase 2

Project Description

Contract R747/2B Dubai Airport Roads Improvements Phase 2, Al Nahda, Dubai – UAE

Client:  RTA
Main Contractor:Yuksel Dubai Construction Co. LLC
Contract Works Value: AED 16,326,729.92
Scope of Work: Infrastructure works including sewerage, drainage, irrigation and water networks
Authority/ Developers: DM, DEWA, RTA, Etisalat/DU
Year Completed:  2009

International City Phase 2 & 3 Infrastructure Works Stage 1

Project Description

International City Phase 2 & 3 Infrastructure Works Stage 1 Sewerage Works, Dubai – UAE

Client: Nakheel
Main Contractor: GMT Consortium
Contract Works Value: AED 63,901,716
Scope of Work: Sewerage Works
Authority/ Developers: DM, NAKHEEL
Year Completed:  2008

DS 137 – Al Mohassina 2nd

Project Description

DS 137 – Al Mohassina 2nd Sewerage & Drainage (C-264)

Client: Dubai Municipality
Main Contractor: Mabani Delma General Contracting Co. (LC)
Contract Works Value: AED 23,601,491.74
Scope of Work: Infrastructural works including Drainage & Sewerage Networks
Authority/ Developers: DM
Year Completed:  2015

Contract CW – 308E – 2008 (Section E)

Project Description

Contract CW / 308E / 2008 (Section E)

Client:  DEWA
Main Contractor: Al Hijaz Mechanical Equipment Co.
Contract Works Value: AED 15,902,086.95
Scope of Work: Installation, testing and commissioning of DEWA 1200dia water transmission line
Authority/ Developers: DEWA
Year Completed:  2011

ADSSC Contract CT 0-11008

Project Description

ADSSC Contract 0-11008 Asset Enhancement Scheme Area – 2 Deep Trunk Sewer from Mps14 To Mps8 P.S.
Client: ADSSC(Abu Dhabi Sewerage Services Company)
Main Contractor: Mabani Delma General Contracting Co. (LLC)
Contract Works Value: AED 40,367,109
Scope of Work: Construction of sewage pumping station
Authority/ Developers: ADSSC
Year Completed:  2015

FEWA Project No: 3W2011

Project Description

FEWA Project No: 3W2011

Client:  FEWA
Main Contractor: Mabani Delma General Contracting Co. (LLC)
Contract Works Value: AED 83,760,000
Scope of Work: Civil & Mechanical works for ductile iron pipeline construction 1200dia/600dia/400dia
Authority/ Developers: FEWA
Year Completed:  2014

R842-2 Improvements of Al Khail Road Junction 19 & 22

Project Description

R842-2 – Improvements of Al Khail Road Junction 19 & 22

Client:  RTA
Main Contractor:Gunal Mapa JV
Contract Works Value: AED 104,468,439
Scope of Work: Infrastructure and ground investigation works for DEWA Water Division, Etisalat, DM Irrigation Dept., DM drainage Dept., WITC (Du) & RTA
Authority/ Developers: DM
Year Completed:  2012

R999-2 – Dubai Water Canal Phase II

Project Description

R999-2 – Dubai Water Canal Phase II – Elevating Al Wasl & Jumeirah Street

Client:  RTA
Main Contractor:impsha State Construction Engrg.Corp. (Middle East) (L.L.C.) Dubai
Contract Works Value: AED 37,376,406.39
Scope of Work: Infrastructural works including Water, Sewerage, Irrigation, Etisalat & Du
Authority/ Developers:DM, DEWA, RTA, Etisalat/DU
Year Completed:  2016

R999-1 – Dubai Water Canal Phase I

Project Description

R999-1 – Dubai Water Canal Phase I – Elevating Sheikh Zayed Road

Client:  RTA
Main Contractor: Gunal & Mapa Construction & Trade Co.
Contract Works Value: AED 79,010,025.86
Scope of Work: Infrastructural works including: Water, Sewerage, Irrigation, Etisalat & Du
Authority/ Developers: DM, DEWA
Year Completed:  2016

0107 – Jebel Ali Hills Package 4

Project Description

0107 – Jebel Ali Hills Package 4, Roads & Infrastructure Works

Client: Meraas Holding
Main Contractor: Ghantoot Road Contracting (LLC)
Contract Works Value: AED 138,250,800
Scope of Work: Infrastructural works including: Water, Sewerage, Irrigation & fire fighting
Authority/ Developers: DM, DEWA, Etisalat/DU
Year Completed:  2016

DS-146/2 – AL Barsha South 2 & 3

Project Description

DS-146/2 – AL Barsha South 2 & 3, Sewerage and Drainage Systems (C672 & C673) – Phase II

Client: Dubai Municipality
Main Contractor: Detech Contracting LLC
Contract Works Value: AED 24,424,000
Scope of Work: Construction of a sewerage and drainage network within Al Barsha South 2 & 3 Area
Authority/ Developers: DM
Year Completed:  2017

The Hills Development Infrastructural Project

Project Description

The Hills Development Infrastructural Project

Client:  EMMAR
Main Contractor: Detech Contracting LLC
Contract Works Value: AED 12,453,000
Scope of Work: Infrastructural works including: Water, Sewerage, Drainage, Irrigation, Etisalat & Du
Authority/ Developers: DM, DEWA, Etisalat/DU, EMAAR
Year Completed:  2017

1ds Dubai Hills Estate Development

Project Description

1dsDubai Hills Estate Development – DM external utilities connections – storm water drainage works

Client:  EMMAR
Main Contractor: Detech Contracting LLC
Contract Works Value: AED 21,750,000.00
Scope of Work: Construction of a 1200mm storm water drainage pipeline
Authority/ Developers: DM, EMAAR
Year Completed:  2019

DS-198/2

Project Description

DS-198/2 : Upgrading of Subsidiary Sewage Pumping Stations G1 – G7

Client: Dubai Municipality
Main Contractor: Detech Contracting LLC
Contract Works Value: AED 153,773,562.00
Scope of Work: Construction of a Sewerage Pumping Station & a 1200mm DIA Sewerage Rising Main
Authority/ Developers: DM
Year Completed: 2020 (Additional Works)

R1048/2 Improvements of Expo 2020 Roads Network

Project Description

R1048/2 Improvements of Expo 2020 Roads Network

Client:  RTA
Main Contractor: China State Construction, Detech Contracting LLC
Contract Works Value: AED 5,499,910
Scope of Work: DM Irrigation Transmission Line Works
Authority/ Developers: DM
Year Completed:  2019

R1045 – Improvements of Interchange Nr. 7

Project Description

R1045 – Improvements of Interchange Nr. 7 on Sheikh Zayed Road

Client:  RTA
Main Contractor: Gunal Construction, Detech Contracting LLC
Contract Works Value: AED 20,000,000
Scope of Work: Infrastructural works including: Water, Sewerage, Drainage and Irrigation
Authority/ Developers: DEWA, DM
Year Completed:  2018

Downtown Dubai Development

Project Description

Downtown Dubai Development – chilled water network looping to plot 44 along road M004 (phase 2 & 3)

Client:  EMMAR
Main Contractor: Detech Contracting LLC
Contract Works Value: AED 8,685,006.00
Scope of Work: Chilled water network looping to plot 44 along road M004 (phase 2 & 3)
Authority/ Developers: EMAAR, TABREED
Year Completed:  2021

Dubai Metro Route 2020

Project Description

Dubai Metro Route 2020

Client:  RTA
Main Contractor: Expolink 
Contract Works Value: AED 442,650,000.00
Scope of Work: Infrastructural works including : Water, Sewerage, Drainage, Irrigation, Etisalat & Du
Authority/ Developers: DEWA, DM, RTA, Etisalat/DU, LOOTAH, TABREED
Year Completed:  2021